EPC pilot project © Seyntex
SEYNTEX

Project Stakeholder

SEYNTEX

EPC in production site Seyntex – Belgium

Facility and Initial Situation

Facility

  • Five buildings with net floor area 34,108m² comprising administration buildings, a textile production site as well as logistics buildings.

Initial Situation

  • Production site in which the processes have been regularly modified, but the supporting infrastructure has not been optimised accordingly.
  • Office building with out-of-date heating system.
  • Logistics buildings (storage) recently refurbished.

Goals and Measures

Goals of building owner

  • Maintain/improve production quality
  • Reduce CO2 footprint
  • Obtain information on specific energy use
  • Ensure profitability

Measures

  • Isolation of hot oil circuit
  • Adjustment of regulation of oil heating system (demand driven)
  • Relighting

Facts

Installation of energy efficiency measures

2016

Duration of the contract

Confidential

Investment

184,055 €

Energy costs 2014 (Baseline)

541,587 €/a

Guaranteed savings in Euro

25,000 €/a

Guaranteed savings in %

5 %

Reduction of CO2 emissions

128 t/a

Innovations and Client’s Advantage

  • Reduction of CO2 emissions, less offset needed
  • Advantages in public tenders
  • Detailed info on specific energy use (e.g. kWh per m textile processed)
  • Less energy cost

Picture: © Seyntex